Performance reports

Reporting on Roads and Maritime's performance against our 2016-2017 Delivery Plan, as at 28 February 2017.

Click a strategic priority to see the list of deliverables for each category.

Making safety paramount

DELIVERABLEStatus

Road Safety

 
Deliver the Safer Roads Program, including State Blackspot TreatmentsIn progress
Deliver Road Safety Behavioural ProgramsIn progress
Deliver the Australian Government Federal Black Spot ProgramIn progress
Deliver the Safety Around Schools ProgramIn progress
Complete 400 sites as part of Stage 4 of the School Zones Alert Signs ProgramIn progress
Deliver the Local Roads – Safety and Congestion ProgramIn progress
Collaborate with National Heavy Vehicle Regulator (NHVR) to review the current service delivery modelIn progress

Aboriginal Road Safety

 
Deliver the 2016-17 Aboriginal Road Safety Infrastructure ProgramIn progress
Deliver bike safety and child car safety seat programs in Aboriginal communitiesIn progress

Safe Boating

 
Manage major special aquatic events including the Sydney to Hobart Yacht Race, Australia Day, New Year’s Eve on Sydney Harbour, Bridge to Bridge events, Southern 80, Extreme Sailing series and Vivid to improve safety for users of NSW waterwaysIn progress
Increase awareness of safe boating through the delivery of boating safety education engagement activitiesIn progress
Deliver statewide boating safety education and compliance campaignsIn progress

Work Health and Safety

 
Implement, in partnership with industry, the second year initiatives in the Roads and Maritime WHS ProgramIn progress

Delivering our infrastructure program

DELIVERABLEStatus

WestConnex

 
Complete the King Georges Road Interchange UpgradeIn progress
Prepare procurement process,  finalise design, commence critical land acquisition and begin property remediation for the WestConnex Stage 3 M4-M5 LinkIn progress
Provide site access for WestConnex in accordance with Project Deed obligationsIn progress
Open WestConnex M4 widening to trafficIn progress

Sydney Motorways Planning and Enhancements

 
Deliver the Western Harbour Tunnel and Northern Beaches Link Study final business caseCOMPLETE
Deliver the F6 Corridor Study final business caseCOMPLETE
Deliver the Sydney Gateway final business caseIn progress
Continue excavation of the mainline for the NorthConnex TunnelIn progress

Western Sydney Infrastructure Plan

 
Complete construction of the new Werrington Arterial Road linking the M4 Motorway to the Great Western Highway, Claremont MeadowsIn progress
Award the construction contract for the upgrade of The Northern Road between Peter Brock Drive and Mersey Road, and the Bringelly Road upgrade between The Northern Road and King StreetIn progress
Award the design and construct contract for the upgrade of The Northern Road between Glenmore Parkway and Jamison RoadCOMPLETE
Display the Environmental Impact Statement for the upgrade of The Northern Road between Mersey Road and Glenmore ParkwayIn progress
Complete the preliminary concept design for the future M12 Motorway linking the M7 Motorway with The Northern Road near LuddenhamIn progress

Pacific Highway

 
Complete construction of dual carriageways on the Pacific Highway between Nambucca Heads and UrungaCOMPLETE
Commence construction of a new road bridge over the Clarence River on the Pacific Highway at HarwoodCOMPLETE
Commence construction (early works) for the additional Grafton bridge over the Clarence RiverCOMPLETE
Commence construction of the Pacific Highway upgrade between Glenugie and TyndaleCOMPLETE
Display the concept design for the Pacific Highway bypass of Coffs HarbourIn progress

Princes Highway

 
Commence construction of the realignment of the Princes Highway at Dignams Creek, south of NaroomaIn progress
Open the Princes Highway bypass of Foxground to traffic, between Toolijooa Road and Austral Park RoadIn progress
Open the new Princes Highway Burrill Lake Bridge to trafficIn progress
Achieve planning approval for the M1 Princes Motorway bypass of Albion Park RailIn progress

Regional NSW Major Road Upgrades

 
Announce the preferred option for the Newell Highway upgrade at ParkesCOMPLETE
Invite construction tenders for the upgrade of the New England Highway at Bolivia Hill, near TenterfieldIn progress

Central Coast Roads

 
Commence construction of the M1 Pacific Motorway widening, Kariong interchange to Somersby interchangeIn progress
Complete construction of the upgrade of the intersection of Wyong Road and Enterprise Drive, Chittaway BayCOMPLETE
Commence construction of the M1 Pacific Motorway widening, between Wyong Road at Tuggerah and the Doyalson Link RoadIn progress
Display the Review of Environmental Factors for the upgrade of the Pacific Highway and Manns Road between Narara and LisarowIn progress

Hunter Roads

 
Open the eastbound New England Highway overpass of the Maitland railway station roundabout to trafficCOMPLETE
Display the Environmental Impact Statement for the Newcastle Inner City Bypass, Rankin Park to JesmondCOMPLETE
Invite construction tenders for the New England Highway bypass of SconeIn progress
Develop and deliver the Hunter Pinch Points ProgramIn progress

Great Western Highway and Bells Line of Road

 
Determine the Review of Environmental Factors for the future upgrade of Chifley Road between Bell and LithgowCOMPLETE
Invite construction tenders for safety works on the Great Western Highway between Katoomba and Mount VictoriaIn progress
Deliver the Bells Line of Road Program of overtaking lanes and safety improvementsIn progress
Complete construction of the four lane upgrade of the Great Western Highway at KelsoIn progress
Complete safety works on the Great Western Highway at Hartley Valley between Mt Victoria and HartleyIn progress

Easing Congestion

 
Develop and deliver the Sydney Clearway Strategy Program 1In progress
Develop and deliver the Gateway to South Pinch Points ProgramIn progress
Develop and deliver Pinch Points ProgramsIn progress
Progress development of the Parramatta Congestion Improvements ProgramIn progress

Established Sydney Roads

 
Commence road widening works on Epping Road from Essex Street to Blaxland RoadIn progress
Deliver the Sydney Centre Access Strategy ProgramIn progress

Sydney Airport

 
Complete construction of the Marsh Street widening near Sydney AirportIn progress
Commence construction of the Wentworth Avenue extension and Joyce Drive widening near Sydney AirportCOMPLETE

Western Sydney Growth Roads

 
Complete construction of the upgrade of Richmond Road between Townson Road and north of Garfield Road, Marsden ParkCOMPLETE
Complete construction of the upgrade of Schofields Road between Tallawong Road and Veron Road, SchofieldsIn progress
Determine the Review of Environmental Factors for the Jane Street and Mulgoa Road infrastructure upgradeIn progress
Complete construction of the upgrade of Old Wallgrove Road between Roberts Road and the M7 Motorway at Eastern CreekIn progress

Meeting customer and community needs

DELIVERABLEStatus

Active Transport

 
Deliver the Active Transport Program in partnership with Councils including:In progress
- Commence construction of a new pedestrian/cycle bridge over the Nepean River between Penrith and Emu PlainsCOMPLETE
- Construct a new shared pathway for cyclists and pedestrians on Windang BridgeCOMPLETE

Noise Abatement

 
Manage the Noise Abatement Program including:In progress
- Review Roads and Maritime guidelines and criteria for the architectural treatment of dwellingsIn progress
- Deliver Noise Walls Program, including at Metcalfe Street, CammerayIn progress

Customer Information

 
Implement the use of Google data for Journey Time Reliability reportingCOMPLETE
Progress initiatives to improve journey time reliabilityIn progress
Progress implementation of real-time traveller information across key metropolitan and rural routesIn progress
Support the implementation of the NSW Government digital licensing programIn progress

Customer Satisfaction

 
Develop initiatives to improve customer satisfaction with service deliveryIn progress
Deliver digital solutions to enhance information for network customers, including access maps for Heavy Vehicles and Boating customersIn progress

Bus Priority Infrastructure

 
Develop and deliver the Bus Priority Infrastructure ProgramIn progress
Develop and deliver the Onroad B-Line Program in collaboration with Transport for NSWIn progress

Maritime Infrastructure

 
Complete the McMahons Point wharf upgrade as part of the delivery of the Commuter Wharf Upgrades PackageCOMPLETE
Support the development and delivery of Boating Now infrastructure projects identified in the Regional Boating PlansIn progress

An organisation that delivers

DELIVERABLEStatus

Asset Management

 
Deliver the Enterprise Asset Management final business caseIn progress
Deliver the Infrastructure Asset Strategy 2020 PlanIn progress

Asset Maintenance Program

 
Invest more than $1 billion in the asset maintenance program to achieve agreed network outcomes including:In progress
Statewide 
Deliver the Delineation Maintenance Program by re-marking 13,000 km of lines on key sections of the State Road NetworkIn progress
Southern Region 
Commence sealing and minor improvement work on the remaining unsealed 5 km length of the Crookwell to Bathurst RoadCOMPLETE
South West Region 
Commence widening and reconstruction of the Riverina Highway, Hume Weir to Bethanga BridgeCOMPLETE
Hunter Region 
Complete detailed design of merge upgrades at the Putty Road intersections at Mount Thorley on the Golden HighwayCOMPLETE
Complete new traffic control signals, widening and turn lanes for the intersection of Victory Parade and James Street, TorontoCOMPLETE
Complete rehabilitation from Kerlew Street to Fletcher Street, Nulkaba on Wine Country DriveIn progress
Western Region 
Complete initial seal on the Silver City Highway at Eurowie, north of Broken HillCOMPLETE
Complete Beni to Merrilea widening on the Golden Highway, west of DunedooIn progress
Complete Marrangaroo Gaps pavement rehabilitation, west of Lithgow on the Great Western HighwayIn progress
Complete southbound carriageway rehabilitation of pavement on the Pacific Highway near Blyths Road, south of Port MacquarieCOMPLETE

Risk-Based and Outcome-Focused Regulatory Services

 
Collaborate with Transport for NSW to establish the Point to Point Transport regulatorIn progress
Deliver the Regulatory Transformation Program to ensure Roads and Maritime is a contemporary, responsive and outcome focused regulatorIn progress

Service NSW

 
Support the transition of motor registry services to Service NSWIn progress

Diversity and Inclusion

 
Deliver the initiatives in the Roads and Maritime Diversity and Inclusion Action PlanIn progress

Enhancing economic and social outcomes

DELIVERABLEStatus

Tolling

 
Complete the Tolling Business Reform Program Phase 1COMPLETE
Deliver Tolling Systems Upgrade Program (TSUP 1)In progress

Environmental Management

 
Deliver a Sydney Harbour cleaning program to reduce the impacts of marine pollution, debris, and hazards to navigation by committing to cleaning Sydney Harbour 365 days of the yearIn progress
Develop a long term litter reduction strategy and implement annual initiatives and programsIn progress
Lead planning and preparedness to respond to level 1 or 2 marine pollution incidents in NSWIn progress

Heritage

 
Publish information about the history of Timber Truss Bridges in NSW from the 19th century to the presentIn progress

Innovation

 
Support Transport for NSW in establishing the Smart Innovation Centre including transition of research related activitiesIn progress
Consistently drive quality and value for money outcomes in delivery and management of Roads and Maritime corporate and commercial servicesIn progress
Complete implementation of Decade of Decentralisation initiatives, including Activity-Based WorkingIn progress
Complete the Proof of Concept for the Premier’s Innovation Initiative “Towards Self-Driving Vehicles”In progress

Aboriginal Programs

 
Deliver Driver Licensing Access Programs to disadvantaged Aboriginal people and other disadvantaged groupsIn progress
Deliver Aboriginal Don't Drink and Drive Programs in each region, including at the NSW Aboriginal rugby league knockoutIn progress

Easing Congestion

 
Deliver final business case for the SCATS Improvement Program (initiatives 1-4)In progress
Coordinate and oversee management of the Sydney Airport precinctIn progress
Commence construction of the Smart Motorways Program for Stage 1 (M4 Widening from Roper Road to M7)In progress

Road Freight Safety and Productivity

 
Announce the preferred option for an additional bridge over the Macquarie River at DubboIn progress
Invite construction tenders for the heavy duty pavement upgrade of the Newell Highway from Mungle Back Creek to BoggabillaIn progress
Deliver the Bridges for the Bush Program including:In progress
- Commence construction of a new Bruxner Highway bridge over the Clarence River at TabulamIn progress
- Commence construction of a second road over rail bridge at GunnedahIn progress