The Pinch Point Program began in November 2006 and is working towards improving journey times on some of Sydney's main corridors.
Intersection treatments
This page shows examples of intersection treatments.









Intersection of Old Windsor Road and Powers Road. Treatment: Widening Powers Road to provide an extra eastbound lane approaching Old Windsor Road. Completed: December 2012
Intersection of Hume Highway and Liverpool Street. Treatment: Install a right turn lane at the Hume Highway northbound into Liverpool Street. Completed: December 2012.
Intersection of Hume Highway and The Horsley Drive. Treatment: Realign the left turn slip lane from Hume Highway eastbound into The Horsley Drive. Completed: December 2012.
Intersection of Camden Valley Way and Campbelltown Road. Treatment: Extension of the dual right turn from Camden Valley Way into Campbelltown Road. Completed: October 2012.
King Georges Road, Beverly Hills. Intersection of King Georges Road and Edgebaston Road. Treatment: install traffic signals. Completed May 2010.
Intersection of Pacific Highway and Herbert Street. Treatment: install closed circuit television (CCTV) for incident management response. Completed February 2009.
Campbelltown Road, St Andrews. Intersection of Campbelltown Road and St Andrews Road. Treatment: widen the existing single lane roundabout and its approach to two lanes. Compled February 2012
Intersection of Campbelltown Road and Ben Lomond Road. Treatment: extend right turn bay and provide dual right turn lanes into Ben Lomond Road. Completed January 2012.
Intersection of Pacific Highway and Greenwich Road. Treatment: extend right turn bay southbound into Greenwich Road. Completed June 2011.