M1 Pacific Motorway to Newcastle - completed

Roads and Maritime Services upgraded six intersections along the 13 kilometre route between the M1 Pacific Motorway at Seahampton and Newcastle. This $50 million project was funded by the NSW Government.

Updates and announcements

Project completed. For more information about the completion of the intersection upgrades, read the August 2013 media release.

Project background

Roads and Maritime carried out the intersection upgrades to improve traffic flow and road safety for all motorists.

The six intersections were selected in 2011 after a study to identify and prioritise future upgrades and subsequent community consultation.

Project timeline

Location Timeframe
Thomas Street / Longworth Avenue intersection Started November 2011 - Completed June 2012
Jesmond roundabout Started November 2011 - Completed July 2012
Croudace Street/Newcastle Road intersection Started December 2011 - Completed end 2012
Douglas Street Started August 2012 - Completed July 2013
Lake Road Started August 2012 - Completed July 2013
Cameron Park intersection Started April 2012 - Completed April 2013