New Grafton bridge - additional crossing of the Clarence River

The NSW Government is funding this $240 million project which involves building an additional 525 metre bridge 70 metres downstream from the existing road and rail bridge. The project also includes upgrading parts of the road network in Grafton and South Grafton to connect the new bridge to the existing road network. The new bridge will consist of two lanes but has been designed to be increased to four lanes when traffic levels require it.

Clarence River crossing at Grafton

Updates and announcements

Work outside of normal construction hours

The new Grafton bridge project team will be working outside of normal construction hours to pour concrete for the top sections of the remaining marine and land piers. The team will do this up to seven times between June and the end of 2018. This June notification (PDF, 517Kb) provides further information.

Changes to Pound and Clarence streets

From Monday, 14 May we will be making some sections of Clarence and Pound streets one-way as we upgrade the roads. Detour signage is in place and access to businesses and properties will be maintained. This change is expected to be in place until early 2019. This May notification (PDF, 265Kb) provides further information.

Work outside of normal construction hours

The new Grafton bridge project will be working outside of normal construction hours on a number of occasions between Monday, 14 May and Saturday, 22 December 2018. This work is so we can enable traffic switches, build driveways to business, build new footpaths, connect services and build pavement. More information is available in this May notification (PDF, 63.3Kb).

Release of operational noise reports

The New Grafton bridge project recently commissioned two reports to compare the predicted future road traffic noise levels from the new bridge to those reported in the Environment Impact Statement (EIS) which was published in 2014.

These reports, the Operational Noise Report (ONR) and the Detailed Noise Modelling and Assessment for At-Property Mitigation (DNMA) are now available to the public.

View or download the:

Please contact the project team if you have any questions.

Building activities

Key building activities planned between April and June include:

  • continuing utility relocation
  • continuing drainage work
  • continue manufacture of bridge segments
  • start piling for additional piles at piers 7 and 8
  • continue building the Kent Street pump station
  • start upgrade of Pound and Clarence streets
  • continuing pier construction in the river
  • start foundation work for the new Pound Street rail viaduct
  • continue construction of the northern approach embankment
  • continue building the new road behind Bunnings.

Project snapshot

  • Contractors: Fulton Hogan
  • Form of contract: Design and construct contract
  • Start date of major construction: November 2016
  • Expected completion date: 2019 (weather permitting)
  • Project value: $240 million.

Project purpose and objectives

  • Enhance road safety for all road users over the length of the project
  • Improve traffic efficiency between and within Grafton and South Grafton
  • Support regional and local economic development
  • Involve all stakeholders and consider their interests
  • Provide value for money
  • Minimise impact on the environment.

Image Gallery

Share this page: