Woolgoolga to Halfway Creek (section 1)

Major work started in July 2015 on the Woolgoolga to Halfway Creek project. Roads and Maritime Services has engaged OHL and York to build the 14 kilometre Woolgoolga to Halfway Creek section of the Woolgoolga to Ballina upgrade.

Dirty Creek Range cutting
Dirty Creek Range cutting

Project overview

Major building work is set to start on this section of the upgrade. Once complete this upgrade will link the Sapphire to Woolgoolga project to the south and the Halfway Creek to Glenugie project to the north, providing 14 kilometres of divided roadway. It is expected that work on Woolgoolga to Halfway Creek section will be finished in 2017.

OHL and York Joint Venture will partner to deliver the section of upgrade between Woolgoolga and Halfway Creek.

The key features of the Woolgoolga to Halfway Creek upgrade include a 300 metre long twin bridge over the Corindi floodplain to allow flood waters to pass under the highway as well as bridges over the highway at Sherwood Creek Road and Kangaroo Trail Road for local road access.

The upgrade is jointly funded by the Australian and NSW governments.

Upcoming activities

October to December 2016

Upcoming work on the project will include:

  • Moving Pacific Highway traffic on to a 1.8 kilometre section of the new northbound carriageway from the southern tie-in at Arrawarra back onto the existing highway south of Tasman Street at Corindi Beach
  • Opening the upgraded section of Eggins Drive from Arrawarra Beach Road to south of the entrance to the Darlington Beach Holiday Park to traffic
  • Completing controlled blasting
  • Continuing surveys and boundary fencing
  • Continuing earthwork and drainage
  • Completing the Cassons Creek, Corindi Creek, Corindi floodplain, Corindi access road and Range Road interchange bridges
  • Property adjustments
  • Building the Corindi access road
  • Continuing crushing and screening of select earthwork material near Hawthorn Close, Corindi Beach
  • Continuing operation of the concrete batch plant near Taylors Run, Corindi Beach
  • Continuing concrete paving and out of hours saw-cutting
  • Monitoring dust, noise and water quality
  • Continuing to upgrade Falconers Lane and The Siding at Dirty Creek, and Eggins Drive at Arrawarra.

Employment opportunities

For employment opportunities on this section contact:

Project documents

Pacific Highway traffic switch at Range Road, Dirty Creek

July 2016

Notification for traffic changes being implemented at Range Road

Access arrangements notification

April 2016

Notification for changed access arrangements at Sherwood Creek Road and Eggins Drive, and Kangaroo Trail Road

Work Notification for Eggins Drive

January 2016

Notification for the Eggins Drive Upgrade

Project update notification

January 2016

Notification of works taking place from January to March 2016

Works notification

November 2015

Changed access arrangements at Rediger Close and Grays Road

Notification for girder placement

November 2015

Temporary highway delays for placement of girders

Proposal letter

October 2015

Proposal to increase blast limits

Fact sheet

October 2015

Controlled blasting facts

Project update notification

October 2015

Notification of works taking place from October to December 2015

Map of the temporary Kangaroo Trail Road side track

July 2015

Major work to start

June 2015

Update on upcoming activities

Community registration form

April 2015

Registration form for the project

Notification of early works between Woolgoolga and Halfway Creek

April 2015

Letter to community outlining early work activities, work hours and contact details