Project flowchart

The process

  1. Preferred option and preferred access options announced- 2009
  2. Draft concept design dsplayed for community comment - April 2012
  3. Refined concept design - March 2013
  4. Review of Environmental Factors display - November 2013
  5. Submissions report - March 2014
  6. Project approval - March 2014
  7. Finalise detailed design / Finalise property purchases
  8. Utility services relocation, Start work to upgrade Cambewarra Road/ Moss Vale Road roundabout, Invite registration of interest for construction work - we are here
  9. Invite tender for construction work - late 2017
  10. Start major construction work - 2018