Project update
March 2018
Upcoming work at Croziers Road and Princes Highway intersection
Resident notification
July 2017
Upcoming night work at Cambewarra and Moss Vale roads roundabout, Bomaderry
Resident notification
March 2017
Work to upgrade the roundabout at Cambewarra and Moss Vale roads, Bomaderry
Detailed design for the highway upgrade
March 2017 - Community update
Addendum Review of Environmental Factors
April 2017
An addendum Review of Environmental Factors has been prepared to assess the likely impacts of the proposed changes on the environment and to outline any additional protective measures to be implemented for the detailed design of the highway upgrade.
Review of Environmental Factors
Submissions report
March 2014
Submissions report provides responses to issues raised in submissions recieved from the community, interest groups and stakeholders during the display of the review of environmental factors. The report also details the changes Roads and Maritime will make to the concept road design, following the feedback received from the community and stakeholders.
Table of contents
November 2013
Review of environmental factors report table of contents and list of tables and figures.
Chapter 2 - Needs and options considered
November 2013
This chapter describes the need, objectives and justification of the project in terms of the strategic vision for NSW (including NSW south coast).
Chapter 3 - Description of the proposal
November 2013
This chapter provides a project description including main project elements, ancillary facilities, design standards and construction activities.
Chapter 4 - Statutory and planning framework
November 2013
This chapter provides an overview of the approval process for the project
Chapter 5 - Consultation
November 2013
This chapter provides an overview of consultation activities that have been and will continue to be carried out for the project.
Chapter 6 - Environmental Assessment
November 2013
This section assesses the potential traffic and transport impacts.
Chapter 7 - Environmental management
November 2013
This chapter describes how the proposal would manage potential environmental impacts throughout detailed design, construction and operation.
Chapter 8 - Conclusion
November 2013
This chapter presents a justification of the project and a conclusion to the review of environmental factors. it considers a range of issues including project benefits, protection of the environment, the objects of the EP&A Act, including ecologically sustainable development and community consultation.
Chapter 9 - Certification
November 2013
Certification of the review of environmental factors.
Chapter 10 - References
November 2013
Report reference list.
Chapter 11 - Glossary of terms and abbreviations
November 2013
Glossary of terms and abbreviations
Table of contents
November 2012
Review of environmental factors report appendices table of contents.
Appendix A - Consideration of clause 228(2) factors and matters of national environmental significance
November 2013
Consideration of clause 228(2) factors and matters of national environmental significance.
Appendix B - Consultation
November 2013
This appendix provides supporting information and further detail on community/stakeholder engagement.
Appendix C - Traffic and Transport
November 2013
This appendix contains the technical paper for traffic and transport.
Appendix D - Noise and vibration
November 2013
This appendix contains the technical paper for noise and vibration.
Appendix E - Terrestrial flora and Fauna
November 2013
This appendix contains the technical paper for flora and fauna.
Appendix F - Aquatic ecology and water management
November 2013
This appendix contains the technical paper for aquatic ecology and water quality management.
Appendix G - Surface water, groundwater and flooding
November 2013
This appendix contains the technical paper for surface water, groundwater and flooding.
Appendix H - Urban design (part 1)
November 2013
This appendix contains the technical paper for Urban design including landscape character and visual amenity - Part 1.
Appendix H - Urban design (Part 2)
November 2013
This appendix contains the technical paper for Urban design including landscape character and visual amenity - Part 2.
Appendix I - Aboriginal cultural heritage
November 2013
This appendix contains the technical paper for Aboriginal cultural heritage.
Appendix J - Non-Aboriginal (historic) heritage
November 2013
This appendix contains the technical paper for Non-Aboriginal (historic) heritage.
Appendix K - Socio-economic
November 2013
This appendix contains the technical paper for socio-economic - Main report and Appendix A to Appendix C.
Concept Design
November 2013
This poster describes the concept design.
How to make a submission
November 2013
This poster describes how to make a submission during the display of the review of environmental factors.
Aboriginal cultural heritage
November 2013
These two posters describe Aboriginal cultural heritage significant places, landscapes and items.
Non-Aboriginal cultural heritage
November 2013
These two posters describe Non-Aboriginal (historic) heritage sites and summary of identified heritage items and potential impacts.
Flora and Forna
November 2013
This poster describes flora and fauna identified in the study area.
Local Access
November 2013
This poster describes the local access arrangements for properties and local roads in the study area.
Community information
Meeting register
November 2013
Berry to Bomaderry upgrade meeting register.
Meeting register
November 2013
Berry to Bomaderry upgrade meeting register.
Issues register
May 2013
Final issues register summarising community raised issues and Roads and Maritime responses on the concept design.
Issues register
May 2013
Final issues register summarising community raised issues and Roads and Maritime responses on the concept design.
Letter to householder
March 2018
Upcoming work at Croziers Road and Princes Highway intersection
Letter to householder
February 2018
Improving safety and accessibility at the Croziers Road intersection before and during major construction of the Berry to Bomaderry Upgrade
Nightwork notification
July 2017
Upcoming night work at the Cambewarra and Moss Vale roads roundabout, Bomaderry.
Letter to householder
September 2013
Update to residents about the investigations carried out by Roads and Martime to address the concerns about Croziers Road access arrangements.
Letter to householder
September 2013
Update to residents about the investigations carried out by Roads and Martime to address the concerns about Croziers Road access arrangements.
Letter to householder
March 2013
Update to residents on teh removal of the proposed heavy vehicle rest area and heavy vehicle inspection bay at Meroo Meadow, as part of the Berry to Bomaderry upgrade.
Letter to householder
August 2013
Update to residents on progress of the Berry to Bomaderry upgrade including publication of an issues register on the website and next steps.
Letter to householder
May 2012
Invitation to additional community meetings. Fourth discussion on draft concept design and heavy vehicle facility location discussion.
Letter to householder
April 2012
Update to residents to advise concept design has been updated and to identify changes to the design.
Letter to householder
March 2011
Update to residents on the progress of the Berry to Bomaderry upgrade and the next steps.
Berry to Bomaderry Frequently asked questions
March 2018
Croziers Road Q&As
September 2013
Roads and Maritime responses to the frequently asked questions about access arrangements at Croziers Road.
April 2015
April 2015
Community update - final concept design road design
March 2013
March 2013
Community update including changes to the refined concept design, final issues register and upcoming Review of Environmental Factors.
Display Poster - March 2013
March 2013
Display poster including changes to the refined concept design.
November 2009
November 2009
Community update with arrangements for local road and property access.
June 2009
June 2009
Community update with preferred option and Gerrignong and berry access options finalised.
October 2008
October 2008
Community update with preferred option and Gerrignong and berry access options.
November 2007
November 2007
Community update detailing route options and the route options display activities.
21 June 2012
June 2012
Meeting notes from 21 June 2012 focus group.
Land acquisition information guide
February 2012
This guide explains what happens when Roads and Maritime Services needs to acquire private land to upgrade roads, build new roads or maintain existing roads. The purpose of the guide is to give people a good understanding of what to expect if their property is affected by land acquisition.
Question & Answers factsheet
November 2011
This fact sheet provides answers to some commonly asked questions on how Roads and Maritime Services acquires private property.
Design
Preliminary Concept Designs
April 2012
Concept design from:
- Schofields lane to Strongs Road
- Strongs Road to Boxsells Lane
- Boxsells Lane to Bomaderry