Frequently asked questions

FAQs

General

  • The NSW Government is upgrading roads around the new Northern Beaches Hospital with work to be completed in time for the hospital opening. The road upgrade includes road widening along Frenchs Forest Road, providing access to the new hospital, intersection improvements with bus priority measures, grade separation on Warringah Road at Forest Way, Hilmer Street and Wakehurst Parkway, new pedestrian bridges and bus stop upgrades.
  • Construction work began in December 2015 and the project is expected to be completed in 2018.
  • The roads surrounding the new hospital experience heavy congestion and queuing at peak times. Significant upgrades to surrounding roads and bus services are needed for the hospital precinct road network to operate effectively.
  • Ferrovial York Joint Venture has been engaged to deliver the project.
  • The road upgrade will:

    • Provide road users with a better travel experience
    • Increase the capacity of the road network to address current and future congestion
    • Improve access and connectivity throughout the area for all road users including motorists, pedestrians and cyclists.
  • This package was announced as part of the NSW Government’s commitment to the Northern Beaches Transport Action Plan, released in June 2014.
  • Please refer to the Environmental Impact Statements for Stages 1 and 2 for the different options considered for the project.

  • The road upgrade will cater for all existing movements currently on Warringah Road and will also provide four additional through lanes. This includes two additional through lanes heading east and two through lanes heading west. At its widest point, Warringah Road will have up to 13 lanes.

Construction

  • Yes. Some of the work will be outside of standard hours of work. The community will be informed before any night work is carried out. Night work is necessary to minimise the impact on the wider road network.
  • Ferrovial York Joint Venture has prepared a Noise and Vibration Construction Management Plan. Noisy equipment and machinery causing vibration will be operated as far from residents and businesses as possible and vibration will be monitored if it is occurring close to buildings. During night work, additional mitigation measures may include using flexible noise shields to dampen noise, where possible, and working in shifts so residents are not affected for more than three consecutive nights per week. The affected community will be informed at least five days before the start of any night work.
  • Any activity likely to impact traffic flows is considered a ‘road occupancy’ and requires a licence issued by the Transport Management Centre. The Road Occupancy Licence (ROL) allows the road to be used and sets out the conditions and approved times for the road occupancy.
  • To prepare for the road upgrade, a number of services throughout the project will need to be relocated. This includes electricity, water, sewer, gas and telecommunications. The project team is working closely with utility and service providers to carry out this work. The work to relocate services involves establishing traffic controls, clearing trees and vegetation, excavating trenches and services pits, boring holes, installing new conduits, pipes, poles and cables, and then transferring services to new infrastructure. There will be some minor interruption to services during cutovers. Affected residents will be notified before any interruptions.
  • Roads and Maritime has investigated the possibility of relocating power lines underground along Frenchs Forest Road West and Naree Road. However, due to the presence of High Pressure gas mains running underground on both sides of the road, new underground electrical power lines would need to be placed at a safe distance from the gas mains for safety reasons. This would place them outside the construction area, and would require the acquisition of land from property owners.

Traffic and transport

  • Once the work is completed, there will be an additional four lanes, increasing capacity for east-west traffic along Warringah Road. All existing lanes will be retained and there will be two new eastbound and two new westbound lanes.
  • Roads and Maritime is addressing parking issues in the area through the Traffic and Access Management Plan. We have consulted with businesses in the area and provided additional parking spaces at the Skyline Shops, The Forest High School, and additional parking on the northern side of Frenchs Forest Road West during off-peak periods.

    If the hospital is acting as a catalyst for change and people are parking on the side streets because of the cost of the parking, the hospital will need to address this issue in conjunction with local Council.

  • Parking is provided for workers at the construction site compound located at the north eastern corner of Wakehurst Parkway and Warringah Road.
  • Changes to bus services to the hospital precinct will introduce two suburban bus routes shown in Sydney’s Bus Future. The aim is for customers to wait less than 15 minutes for weekday suburban bus services to the hospital precinct on routes connecting Manly to Chatswood via Dee Why and Frenchs Forest and Belrose to the Sydney CBD via Eastern Valley Way.
  • During construction, some bus stops need to be temporarily relocated or closed. These changes have and will continue to be communicated to the community via notification letters and signs posted at the bus stops. These changes and modifications are approved by Transport for NSW. The project team consults regularly with transport providers, local Council and other stakeholders on these bus and transport changes.
  • Maxwell Parade is outside the project boundary and no major modifications are planned for this intersection. Upon completion of the project, it is anticipated all movements currently available at Maxwell Parade intersection would be maintained, provided public safety is not compromised.

Pedestrians and cyclists

  • The project will include new shared bridges (pedestrian and cyclist):

    • Across Warringah Road west of the intersection of Forest Way (removal and replacement of the existing pedestrian bridge)
    • Across Warringah Road on the western side of the intersection with Hilmer Street

    In addition, the road upgrades will provide shared paths (pedestrian and cyclist) and footpaths on sections of Warringah Road, Wakehurst Parkway, Forest Way, Aquatic Drive and Allambie Road.

  • During construction, there will be some impact such as redirecting pedestrians and changing locations of crossings, however pedestrian access will be maintained at all times during the project.

Environment

  • The impacts of the project have been examined thoroughly in the Environmental Impact Statements (EIS) which provide details of expected impacts and outline measures to manage and mitigate these impacts. These impacts include environment, noise, vibration, biodiversity, land use, heritage, air quality, flora and fauna. These documents are available on the Roads and Maritime and the Department of Planning and Environment websites.
  • The project will result in the removal of trees and vegetation, including some Duffys Forest vegetation, which is an endangered ecological community. The removal of Duffys Forest is considered a significant impact because less than 16 per cent of the original area of Duffys Forest currently exists in the region.

    Strict environmental controls and processes are in place, as outlined in the EIS, Construction Environmental Management Plans, and the Conditions of Approval from the Department of Planning and Environment. Only those trees necessary for the road project are being removed.

    To offset the removal of vegetation, ‘Biodiversity offsets’ are proposed which could include measures like protection and conservation of an area of land with similar conservation value.

    Roads and Maritime is also exploring options for revegetation using local seeds sourced from within the area. Revegetation will be carried out within the construction zone and delivered progressively.

    Pre-clearance surveys are carried out by the Project Ecologist before any work. These surveys confirm the vegetation from an Ecological perspective on-site before clearance.

    A Construction Flora and Fauna Management Plan will be in place to ensure appropriate measures are in place to protect the environment during construction, including establishing exclusion zones and regular monitoring.

  • Trees are being removed along the southern side of Warringah Road. This area is road reserve and has been set aside in readiness for the road widening. The trees in this road reserve are not native to the area and were planted by the previous roads authority to provide temporary vegetation.

    Where possible, trees will be protected within the project zone and used as part of the final urban design and landscape plan.

    Strict environmental controls and processes are in place, as outlined in the Environmental Impact Statements, Construction Environmental Management Plans, and the Conditions of Approval from the Department of Planning. Only those trees necessary for the road project are being removed.

  • Roads and Maritime is exploring options for revegetation using local seeds sourced from within the area. Revegetation will be carried out within the construction zone and delivered progressively.

    To offset the removal of vegetation, the replanting program will include Indigenous vegetation, particularly Duffys Forest species. ‘Biodiversity offsets’ are also proposed which could include protection and conservation of an area of land with similar conservation value.

    As well as planting trees inside the project site, we will be engaging with property owners and encouraging the additional planting of trees at the front of private properties to further enhance the bush and forest landscape of the area.

  • A wide variety of native species are proposed, including Banksia, Gum trees, Eucalyptus, Bottle Brush, Wattle, Boronia, Grevillea, and many more.

    A full planting schedule can be found in the Urban Design and Landscape Plan.

  • Many species of fauna are found within the area, including mammals, birds, reptiles and amphibians. As part of the EIS, extensive studies have assessed the potential impact of the project on these fauna and outlined measures to avoid or minimise any impacts.

    During clearing an independent ecologist is on site to ensure no animals are harmed and any found are relocated to a safe habitat. The ecologist also identifies any hollow bearing trees and helps determine suitable locations for next boxes.

    To ensure fauna can safely access vegetation, rope bridges and fauna culverts will be included where appropriate, with input from ecological specialists.

    Fauna fencing would be used to minimise the possibility of vehicle strikes to ensure no animals are harmed and any found are relocated to a safe habitat.

Urban Design and Landscape Plan

  • The final design of the road will be contained in the Urban Design and Landscape Plan (PDF, 86.5Mb). The Plan included designs for the underpass, pedestrian bridges and paths, landscaping and vegetation, noise wall, and road furniture (lighting, signage, shelters). Community feedback on the draft Plan closed on 23 June 2016. We thank the community for their comments, which are now being considered as part of the final UDLP.
  • Details of the design of the Warringah Road underpass will be contained in the final Urban Design and Landscape Plan. Community feedback on the draft Plan closed on 23 June 2016. We thank the community for their comments, which are now being considered as part of the final UDLP.
  • Details of the final design of pedestrian and shared bridges will be contained in the final Urban Design and Landscape Plan. Community feedback on the draft Plan closed on 23 June 2016. We thank the community for their comments, which are now being considered as part of the final UDLP.
  • Placing the noise wall along the rear property boundary provides a superior urban design outcome by allowing the adjacent shared path and landscaping area to be in open view of all road users travelling along Warringah Road. Placing the noise wall close to the road would close in the shared path and landscaping area and create an unsafe and hostile environment for pedestrians and cyclists.
  • Yes. The shared footpath will be located between the noise wall and the road. The design of the shared pedestrian and cyclist path between the noise wall and the road must be safe. Users of these facilities must be visible and appropriate lighting will also be provided to ensure facilities and users are visible at night. By designing for crime prevention and carefully considering other important urban design requirements it will create an open and safe environment next to the roadway that also provides suitable noise mitigation for sensitive receivers.
  • The final design of the noise wall will be contained in the final Urban Design and Landscape Plan. The wall will range in height from 3 to 4 metres, depending on the location, with the top section made of an opaque plexiglass. This design has been selected to reduce the visual bulk of the noise wall, minimise overshadowing into private properties, and reduce the structural weight of the noise wall.
  • Two different materials have been proposed for the noise wall panels. The first is a precast concrete panel and the second a Rotationally Moulded Plastic (RMP). Both these materials have been proposed for a variety of reasons, including to reduce the visual bulk of the noise wall, ease of installation and ongoing maintenance. A simple horizontal relief pattern will be provided on the public facing side. The proposed colour will be a recessive grey charcoal, providing a backdrop to the tree, shrub and ground cover planting located between the shared path and noise wall. A decision will be made regarding the final choice of materials after a thorough investigation. The top portion of the wall will be an opaque plexiglass with a frameless top, and include provision for an embedded horizontal frit to minimise possible bird strike. The opaque panels will be installed to minimise overshadowing into private backyard spaces and to reduce the structural weight of the noise wall.
  • A simple horizontal relief pattern will be provided on the public facing side of the noise wall to deter graffiti. The RMP panels are graffiti-resistant and do not require an additional treatment to be applied.
  • Construction will begin as soon as we have received final approval from the Department of Planning and Environment, and all residents have agreed to the proposed design.
  • The back fences for residents on the northside of Karingal Crescent may need to be removed to allow for the construction of the noise wall.
  • Every property is different, and a property assessment will be carried out to determine which back fences will need to be removed.
  • The strip of land between the noise wall and private properties is part of the road reserve and should be treated in the same manner as the road reserve between a front boundary and the kerb and gutter. Property owners have the use and access to the strip, however it may be altered at any time by the authority responsible for the road reserve.
  • Roads and Maritime would not recommend any improvements be made on the strip of land. While property owners have the use and access to the strip, it may be altered at any time by the authority responsible for the road reserve.
  • Temporary fencing will be placed along your boundary during construction of the noise wall to keep your property secure.

Community

  • Community feedback has been integral to the development of the Northern Beaches Hospital Road Upgrade Project.

    Engagement with the community, businesses and other stakeholders has been ongoing since March 2014.

    Environmental Impact Statements were placed on public display in 2014 and 2015, and the community were invited to provide submissions on the project. All feedback received was carefully considered and many changes to the project have occurred in response to community issues.

    In June 2016, community feedback was sought on the draft Urban Design and Landscaping Plan (UDLP). This feedback is being currently considered before finalising the UDLP.

    Engagement activities include door knocking, letterbox drops, email updates, community information sessions, meetings, work notifications, information on the Roads and Maritime website and one-on-one in person and telephone conversations with the community. The project team regularly meet with key stakeholders including Local Council, local schools, businesses, community groups and residents.

    The Community Information Centre has been established at the corner of Warringah Road and Wakehurst Parkway. Information about the project is available to view and members of the project team are available to answer questions. The site will be in place for the duration of the construction. The centre is open from 9am to 5pm, Monday to Friday, and visitor parking is available on site. Disabled access is provided.

  • Contact the Community Information team on 1800 014 307 or email nbhcommunity@ferrovialyork.com.au, and ask to be added to the distribution list.
  • Please contact the Community Information team on 1800 014 307 or email nbhcommunity@ferrovialyork.com.au.

Frenchs Forest Road and Naree Road traffic changes

  • Frenchs Forest and Naree Road will temporarily become one way in a westbound direction (towards Chatswood) for road construction work for up to ten months from Sunday 8 October. Eastbound traffic (towards the beaches) will be diverted and detoured along Warringah Road.
  • These traffic changes allow for the widening and upgrading of Frenchs Forest Road between Patanga Road (near Allambie Road) and Forest Way. The changes are required so we can carry out the road upgrade in time for the new hospital opening in October 2018.

    This construction methodology is quicker and safer for motorists and traffic controllers working on the site and will substantially reduce the amount of night work required along Frenchs Forest Road and Naree Road.

  • This phase of construction involves drainage work, road widening, road work, footpath work, utility work, drainage work and some driveway adjustments to properties along Frenchs Forest and Naree Road.
  • The one way traffic switch begun on Sunday 8 October and during the first few days there were longer traffic delays than expected.

    We listened to your feedback and monitored what was happening, and are implementing some measures to ease the congestion including:

    • Continuing to proactively manage the traffic signal network to accommodate the changing traffic environment
    • Providing traffic advice on electronic message signs in the Northern Beaches and on major approaches  
    • Providing a kiss and ride facility (PDF, 144Kb) on Frenchs Forest Road in front of Forest High School.

    Long term measures include:

    • Fast-tracking the bus bay extensions on Forest Way
    • Installing additional CCTV cameras to monitor traffic
    • Making the south-bound kerbside lane on Forest Way approaching Warringah Road left turn only (buses excepted).

    Roads and Maritime will continue to monitor the change and work closely with the Transport Management Centre and the community.

    Please continue to allow extra time and plan your journey, particularly students sitting their HSC exams.

    Thanks again everyone for your patience.

  • After the construction work is complete, Frenchs Forest Road and Naree Road will be a dual lane carriageway in both directions.
  • Properties with driveways fronting Frenchs Forest Road and Naree Road will be impacted for up to five days during a rolling schedule of work while a new driveway is poured and set. Driveways will be reinstated on a like-for-like basis, that is, using a similar material to the existing driveway. The driveways will be tied-in to the widened and upgraded road level. There is no cost to the owner for the new driveway. All residents will be contacted to discuss the driveway adjustment work at their property prior to the work commencing.

    Vehicles will be unable to access affected driveways for up to five days, weather permitting. We will provide advance notice of up to five working days before the start of work and discuss arrangements for alternative parking with affected residents.

  • Night work occurred on Saturday 7 October to put the new traffic arrangements in place. The traffic changes will allow for a reduction in the overall amount of night work required, however some night work may be required at times. Where night work is required, it will be in accordance with our environmental licence and residents will be notified in advance,

  • Footpaths for pedestrians and cyclists will be maintained at all times throughout this period. However, there may be minor temporary detours in place. Signage and traffic controllers will be in place and available to assist.

    Pathways to the new bus stops will include lighting, reflectors and line marking to guide bus customers to Warringah Road.

  • Yes. Eastbound bus stops on the northern side of Frenchs Forest Road will be temporarily closed and two temporary alternative bus stops will be opened on Warringah Road.

    Signage will be in place to assist pedestrians with the changes. Transport for NSW will have ‘pink shirt’ staff at the closed bus stops to assist commuters during the first week of the changes.

    Passengers will need to walk an extra 200-600m to one of two new bus stop locations. One temporary bus stop will be located on Warringah Road near Forest High School. Pedestrians will be able to access this bus stop through the pedestrian walkway/laneway between The Forest High School and the new hospital.

    The other bus stop will be located near the Parkway Hotel on Warringah Road. Pedestrians will be able to follow the yellow line marking through the car park of the Parkway Hotel, 5 Frenchs Forest Road East, to Warringah Road.

    View or download the detour map (PDF, 256Kb) of the changes. To obtain hard copies of the bus maps, please contact the Community Team. For more information and to plan your trip on public transport, visit transportnsw.info.

    We engaged with over 30 schools throughout the area prior to the school holidays to ensure students, parents and carers were supplied with updated bus information that may impact access and journeys to school upon their return on 9 October.

  • Postal deliveries, garbage pickup and emergency access will be maintained during this rolling program of work.

    Maintained footpath access will allow continued postal deliveries and arrangements are being made to ensure uninterrupted garbage collection at all properties. All residents will be contacted individually to discuss the impact to their property and driveways.

    Emergency access will be maintained at all times and up-to-date information will be provided to residents and businesses during the construction period.

    Emergency services including Fire & Rescue NSW were also involved in the planning of the one way arrangement.

  • Delivery access will be available to all streets and properties, just like any other vehicle.

    If you are planning any large deliveries, we would recommend you contact the Community Team to help coordinate the delivery with you and the construction team.

  • The best route is to travel northbound along Rabbett Street, turn left onto Adams Street, then turn left at the traffic lights onto Forest Way to travel southbound.

    Naree Road will also form oart of the one scheme together with Frenchs Forest Road West so motorists exiting Rabbett Street can turn left at Naree and then left again onto Forest Way. The Adams Street detour would service motorists heading north.

  • There will be no change to the current turning arrangements at Forest Way and Adams Street. Roads and Maritime and the Transport Management Centre are monitoring conditions and will adjust signal phasing to manage traffic flow in the area. This phasing arrangement will be temporary until the upgrade of the intersection of Naree Road and Forest Way is complete, which will include a right turn bay and traffic lights.

    There is an existing right turn arrow into Adams Street, however, this red arrow is present to protect pedestrians crossing Adams Street.

    A right turn green arrow cannot be provided on Forest Way onto Adams Street as right turn arrows are only efficient at traffic lights when there is room for a permanent dedicated right turn bay. In addition, a right turn green arrow phase would cause significant delays to other motorists and users of the intersection. However, to facilitate the movement of right turning traffic the following measures have been put in place:

    • the traffic arrangement has been adjusted to provide a temporary dedicated right turn bay
    • the stop line on Adams Street has been moved back to provide traffic turning right onto Forest Way with more space to turn out safely and with more efficiency. This is particularly helpful to buses and will improve their use of the intersection
    • additional green time has been allocated to Forest Way to assist the traffic turning right into Adams Street.
  • This traffic movement has been removed for safety reasons during construction, and to allow for the long term temporary lane closure along Forest Way between Warringah Road and Adams Street.
  • Yes, vehicles can exit Patanga Road to turn left and right. Vehicles heading westbound along Frenchs Forest Road can turn right into Patanga Road.
  • A westbound one way arrangement is a much safer option for the 1000 students attending The Forest High School. An eastbound arrangement would force students to cross the road to access buses and cars.

    A review of traffic conditions by Roads and Maritime and Transport for NSW has shown that maintaining the westbound direction has a number of advantages over eastbound in the performance of the surrounding road network. The westbound direction is also a heavier traffic movement.

    Westbound bus travel is also the dominant public transport direction so this arrangement minimises the impact to local services.

  • We have carried out detailed investigations and consultation with the Transport Management Centre and Transport for NSW to assess the impact of the changed traffic arrangement on local traffic conditions as well as the wider network.

    We expect some additional congestion and delays on Warringah Road eastbound, Forest Way southbound and Wakehurst Parkway southbound, particularly during the afternoon peak period.

    We apologise for any inconvenience caused and encourage motorists to allow extra travel time.

  • The project team has prepared extensive traffic management plans for the changes, in consultation with a number of stakeholders including Council, Transport for NSW, emergency services and transport providers. These plans have been approved by the Transport Management Centre, Transport for NSW and Roads and Maritime Services.
  • Temporarily converting Frenchs Forest Road to one way is an essential requirement to ensure the Stage One road upgrade are completed in time for the opening of the new Northern Beaches Hospital.

    In developing the traffic management plan, Ferrovial York Joint Venture (FYJV) and Roads and Maritime Services consulted with major stakeholders including Northern Beaches Council, NSW Police Force, Fire & Rescue NSW, Transport for NSW, State Transit, Forest Coach Lines, NSW Taxi Council and more.

    FYJV and Roads and Maritime have provided residents and the community with information on detours, local access and bus stop closures to help plan for the changes.

  • We are committed to minimising the impact of construction and will continue to keep the community informed as the project progresses. For more information or to report any concerns, please contact our delivery partner, Ferrovial York Joint Venture.

Fitzpatrick Avenue East intersection changes

  • Roads and Maritime Services are upgrading the intersection of Fitzpatrick Avenue East and Warringah Road as part of the Northern Beaches Hospital road upgrade project.

    To allow for the intersection to be upgraded access in and out of Fitzpatrick Avenue East is temporarily closed for up to eight weeks starting from Monday night 30 October (weather permitting).

    When the work is complete, the left turn in and left turn out will be reinstated allowing access to and from Fitzpatrick Avenue East onto Warringah Road.

  • Work includes:

    • installing temporary footpaths while the existing concrete kerbs, gutters and footpaths are being removed
    • disposing of the old concrete kerbs, gutters and footpath
    • installing new stormwater drainage lines
    • milling existing asphalt and excavating to the new pavement depth
    • constructing new pavement
    • installing new concrete kerbs, gutters and footpaths.
  • This work is complex and requires significant preparation to ensure it is completed safely and complies with relevant standards.

    The work will involve the use of heavy machinery and will be noisy. As a result, the work will take place mostly during standard daytime hours between 7am and 6pm, Monday to Friday, and between 8am and 1pm on Saturday.

  • There will be some night work required during the eight weeks. The project is strictly regulated by an Environment Protection Licence (EPL) and our Conditions of Approval, which instruct the project can only work at night for a maximum of three nights per week for high noise activities, to ensure local residents are given respite from the noise.
  • No. All access at this intersection is closed during the work.

    Motorists can access Fitzpatrick Avenue East from either Hilmer Street which has reopened to two-way traffic and is a full signalised intersection, or use Currie Road when travelling westbound along Warringah Road.

  • As per current arrangements, motorists can make a left turn out of Hilmer Street into Warringah Road, then a right turn at Forest Way and a left turn at Russell Avenue.

    You could also consider parking on the southern side of the new ForestWay pedestrian bridge near Akora Street or Karingal Crescent and walking across the bridge directly to the school.

  • As per current arrangements,motorists cannot turn right into Fitzpatrick Avenue East when travelling in an eastbound direction. Motorists would have the choice of turning right at Maxwell Parade and then left onto Parni Place or turning right into Hilmer Street.
  • Local streets are not designed to carry the volume of cars which main roads such as Warringah Road carry every day. The restrictions that are placed on these roads are to ensure they are used by local residents and do not become rat runs which poses risks to pedestrians and motorists.

    Additionally, vehicles using these roads as rat runs to avoid congestion on the main roads, will eventually try to find their way back on the main roads at key intersections further south such as Brown Street and Currie Road and Starkey and Ferguson streets. This would then affect the amount of green time allocated to Warringah Road resulting in even longer delays.

  • Local residents will be able to continue to turn right fromWarringah Road into Hilmer Street and then into Fitzpatrick Avenue East. Or they can turn left into Maxwell Parade.
  • The detour volumes are not high enough to require the removal of on street parking at this location. There is also anecdotal evidence cars travel slower down streets with on street parking therefore making the local streets safer during this closure period.
  • The Hilmer Street traffic light operations are being investigated. The intersection will continue to be monitored by the Transport Management Centre.
  • Speed reductions are currently in place and are being enforced along Warringah Road. Electronic message boards show road condition changes.

    Motorists can get the latest traffic updates by contacting 132 701, visiting livetraffic.com or downloading the Live Traffic NSW App.

  • Yes. Emergency access will be maintained at all times.
  • No. Pedestrian access will remain unchanged.
Share this page: