Project documents - Northern Beaches Hospital

Frequently Asked Questions

October 2017

Faq's on Fitzpatrick Avenue East closure

Project notification

October 2017

Fitzpatrick Avenue East closed from Monday 30 October

Project notification

October 2017

Installation of additional site compound and laydown area from Monday 23 October

Project notification

October 2017

Hilmer Street re-opens from Friday 6 October 2017

Project update

August 2017

Wakehurst Parkway closure

August 2017

Closure of Wakehurst Parkway from Friday 11 August until Monday 14 August

Hilmer Street intersection upgrade

July 2017

Hilmer Street intersection upgrade from Monday 24 July

Slip lane opening at Wakehurst Parkway

June 2017

Slip lane opening at corner of Wakehurst Parkway and Frenchs Forest Road East from Tuesday 30 June

Temporary closure of Warringah Road

June 2017

Temporary closure of Warringah Road for installation of the new pedestrian bridge at Hilmer Street on Saturday 24 June

Demolition of old pedestrian bridge

May 2017

Full closure of Warringah Road during demolition of old bridge

New site compound

May 2017

Installation of additional site compound at 500 Warringah Road

Relocation of power poles

April 2017

Relocation of power poles, Frenchs Forest Road East

Installation of pedestrian bridge

April 2017

Full closure of Warringah Road during installation of pedestrian bridge

Installation of Forest Way bridge

March 2017

Night work to install pedestrian bridge across Warringah Road

Ongoing service relocation work

March 2017

Day and night work for electrical, communications, stormwater, drainage and gas relocation

Traffic changes on Forest Way

March 2017

Traffic changes on Forest Way and Naree Road

New site compound

March 2017

Installation of additional site compound at Dreadnought Road

Ongoing service relocation and stormwater drainage work

December 2016

Day and night work on Frenchs Forest Road, Naree Road, Forest Way, Patanga Road, Rabbett Street and Cobb Street.

Ongoing service relocation work

December 2016

Day and night work along Warringah Road corridor

Tree Clearing Update

September 2016

Tree clearing continues on Warringah Road, Wakehurst Parkway and Forest Way

Installation of additional site compound and haul route

August 2016

Installation of additional site compound and haul route

Ongoing night work

August 2016

Ongoing night work along Warringah Road, Frenchs Forest

Further service relocation work

August 2016

Underboring on Warringah Road, near Fitzpatrick Avenue

Reduced speed limits

August 2016

Speed limits reduced on Warringah Road, Wakehurst Parkway, Forest Way and Allambie Drive.

Groundwater bore installation

August 2016

Groundwater monitoring bore at Akora Street

Vegetation removal

August 2016

Tree and vegetation removal on Warringah Road

Service relocation night work

July 2016

Night work on Frenchs Forest Road, Naree Road and Forest Way

Ongoing service relocation night work

July 2016

Night work trenching and underboring on Warringah Road, east of Wakehurst Parkway

Poltholing night work

June 2016

Potholing and identifying services on Warringah Road, near Rodborough Road

Service installation night work

June 2016

Night work service installation across Warringah Road, near Fitzpatrick Avenue

Closure of Bantry Bay Road

June 2016

Bantry Bay Road closed at intersection of Warringah Road

Reduced speed limit

June 2016

Speed limit reduced on Frenchs Forest Road and Naree Road

Service installation night work

June 2016

Service installation on Warringah Road and Forest Way

Ongoing service relocation

June 2016

Service relocation continues on Frenchs Forest Road, Naree Road and Forest Way

Speed bump modification

May 2016

Night work on Frenchs Forest Road West and Naree Road

Service relocation work

April 2016

Day and night work on Forest Way and Naree Road

Night work

April 2016

Removal of median strip and refuge island, Wakehurst Parkway and Frenchs Forest Road East

Preparation work

April 2016

Preparation work along the road reserve, Warringah Road, near Karingal Crescent

Night work

April 2016

Trimming and removing vegetation on Warringah Road

Night work

April 2016

Removal of vegetation on Forest Way

Property demolition

March 2016

Demolition of properties on Warringah Road

Property demolition

March 2016

Demolition of former Bantry Bay Shops

Night work

March 2016

Night work for geotechnical investigations

Service relocation work

March 2016

Trenching and underboring day and night work notification

Additional site compound

March 2016

Installation of additional site compound

Night work

February 2016

Preparation work for power pole relocation

Night work

January 2016

Night work on Forest Way and Russell Avenue

Night work

December 2015

Night work and field investigations during January 2016

Construction Environmental Management Plan

August 2016

This plan provides a structured approach to the management of environmental issues during construction.

Appendix B1 - Traffic and Access Management Plan

August 2016

Details how traffic will be managed during construction.

Appendix B2 - Flora and Fauna Management Plan

August 2016

The plan to minimise impact on flora and fauna during construction.

Appendix B3 - Noise and Vibration Management Plan

August 2016

Details how noise and vibration will be managed during construction.

Appendix B4 - Soil and Water Quality Management Plan

August 2016

Details how soil and water quality will be managed and protected during construction.

Appendix B5 - Heritage Management Plan

August 2016

Describes how Aboriginal and non-Aboriginal heritage will be protected and managed during construction.

Appendix B6 - Air Quality Management Plan

August 2016

Outlines how air quality will be protected and managed during construction.

Appendix B7 - Waste and Energy Management Plan

August 2016

Outlines how waste will be managed and energy consumption will be reduced during construction.

Appendix B8 - Construction Compound and Ancillary Facilities Management Plan

August 2016

Assesses the impact of construction and use of site compounds and ancillary facilities on the community and environment.

Appendix A9 – Compliance Tracking Program

April 2016

Outlines the methods to track compliance with the requirements of the project approvals.

Pre-Construction Compliance Report

May 2016

Addresses the requirements of the Stage 2 Conditions of Approval.

Six Monthly Compliance Report

June 2016

Addresses the requirements of the Conditions of Approval for the first six months (December 2015 – June 2016).

Community Communication Strategy

August 2016

Outlines the strategy for engaging with the community and stakeholders during construction.

Community Consultation Report

October 2014

Community Consultation Report

July 2014

Community Update

November 2016

Northern Beaches Hospital road upgrade project - construction update

Community Update

April 2016

Northern Beaches Hospital road upgrade project - construction update

Community Update

January 2016

Community Update

July 2015

Northern Beaches Hospital Road Connectivity and Network Enhancement Project update

Community update

May 2015

Parking arrangements at Skyline Shops, Frenchs Forest

Community update

May 2015

Environmental Impact Statement - Concept Proposal and Stage 1 Submissions Report

Community update

December 2014

Community update

October 2014

Community update

July 2014

Feedback form

May 2014

Northern Beaches Hospital – connectivity and network enhancements

Community update brochure

March 2014

Community update regarding the Northern Beaches Hospital - Connectivity and network enhancements

Options Report

December 2014

Flora and Fauna

August 2016

Share this page: