Bringelly Road Upgrade Stage 2

Bringelly Road, Bringelly
Bringelly Road, Bringelly

Updates and announcements

Project snapshot

•    Contractor: TBA
•    Start date of major construction: mid-2017
•    Expected completion date: mid-2020
•    Project value $509 million
•    Funding: Australian and NSW governments.

Project background

Roads and Maritime Services is delivering the $509 million Bringelly Road Upgrade in two stages. Stage 1 is from Camden Valley Way, Leppington to King Street, Rossmore. Stage 2 is from King Street, Rossmore to The Northern Road, Bringelly.

Roads and Maritime has finalised the detailed design for Stage 2. We expect to start construction in mid-2017 and be open to traffic in mid-2020.

Benefits

  • The key benefits of the project are:
  • Increased capacity for traffic growth and improved travel times in the future
  • Improved safety for motorists
  • Improved safety for cyclists and pedestrians
  • Better bus priority and facilities
  • Improved access to the Western Sydney Airport at Badgerys Creek, the new Leppington Railway Station and the M5 and M7 motorways
  • Improved access and travel times for road freight in Sydney’s south-west
  • Access to the future South West Growth Centre precincts along Bringelly Road
  • Landscaping consistent with other main road upgrades.

Key features

  • Upgrading from two lanes to a four lane divided road with a central median, which would allow for widening to six lanes, when required
  • A speed limit of 80 km/h
  • A three metre wide off road shared pedestrian and cyclist path with crossings at traffic lights to improve safety
  • Designated turning lanes at traffic lights along with bus priority and indented bus bays on both sides of Bringelly Road
  • New three way intersection at Kelvin Park Drive with traffic lights
  • New four way intersection at Jersey Road with traffic lights and a temporary U-turn facility
  • New bridges over South Creek
  • New four way intersection at Masterfield Street with traffic lights
  • Left in/left out intersection at Church Street
  • Left in/left out intersection at Allenby Road
  • New four way intersection at North Avenue with traffic lights and a temporary U-turn facility
  • Left in/left out intersection at Glen Allen Road.

Community involvement

Community involvement has informed the access strategy, concept design and Review of Environmental Factors, carried out in 2011.  Our response to community submissions can be found in our project documents.

What happens next?

Roads and Maritime is progressing the project and expects to award the construction tender in the coming months.

We expect to start construction in mid to late 2017 and open to traffic in mid-2020.

Share this page: