Stage 2 - Raby Road to Oran Park Drive

Stage 2 of the 3 kilometre section of the Camden Valley Way upgrade, between Raby Road and Oran Park Drive, was completed ahead of schedule and opened to traffic on Sunday 9 November 2014.

Aerial view of Camden Valley Way Stage 2. Copyright: www.skyviewaeerial.com.au
Aerial view of Camden Valley Way Stage 2. Copyright: www.skyviewaeerial.com.au

Project overview

Roads and Maritime Services awarded the construction contract for this stage of work to Nace Civil Engineering Pty Ltd in December 2012.

Construction started in mid-March 2013 and was opened to traffic on Sunday 9 November 2014.

The main features of the upgrade between Bringelly Road, Leppington and Oran Park Drive, Harrington Park are:

  • Two lanes upgraded to a four lane divided road with a wide central median that will allow widening to six lanes when required in the future
  • A speed limit of 80km/h
  • A three metre wide, off road shared pedestrian/cyclist path on the western side of the road
  • Traffic lights at Forest Lawn Memorial Gardens Cemetery, Cowpasture Road south, Heath, St Andrews, Raby, Catherine Field and Springfield roads
  • Realignment of Denham Court Road and Ingleburn Road as a four way intersection with traffic lights
  • Bridges over the Sydney Catchment Authority Water NSW Upper Canal and Bonds Creek
  • Landscaping of the central median consistent with other upgraded sections of Camden Valley Way
  • Bus priority lanes at traffic lights and indented bus bays on either side of Camden Valley Way.

View or download a community update including the road design features.