The Cumberland Highway & Cabramatta Road intersection, Cabramatta

The NSW Government is funding this project at the intersections of Cumberland Highway with Cabramatta Road and Cumberland Highway with Links Avenue, as part of its $225 million Pinch Point Program, which aims to reduce delays, manage congestion and improve travel times on Sydney’s major roads, particularly during peak periods.

Updates and announcements

We are continuing construction on the intersection of Cabramatta Road and the Cumberland Highway.

To complete the next stage of the project, we will work for another 80 night shifts from Monday 6 March to Saturday 3 June, weather permitting. Our night work hours will be between 8pm to 5am.

We will also be working during the day. Our daytime work hours will be between 7am to 6pm, excluding Sundays and public holidays.

View or download the March 2017 Project Update for more information.

Project background

The NSW Government is funding a proposal at the intersection of Cumberland Highway and Cabramatta Road, Cabramatta this project as part of its $225 million Pinch Point Program, which aims to reduce traffic delays, manage congestion and improve travel times on Sydney’s major roads particularly during weekday peak periods.

Project features

  • Extending the third northbound lane on the Cumberland Highway from Cabramatta Road to the bridge over Cabramatta Creek. This would include widening in the Links Avenue intersection
  • Extending the Cumberland Highway southbound and northbound right turn bays
  • Converting the southbound bus lane on the Cumberland Highway to an additional through lane
  • Extending the Cabramatta Road westbound right turn bay
  • Converting the Cabramatta Road eastbound right turn bay into a dual right turn bay
  • Converting of the Cabramatta Road eastbound left slip lane into a through and left turn lane
  • Improving traffic light phasing on the Cumberland Highway at the intersections of Cabramatta Road and Links Avenue
  • Removing shrubs in the median and replacing the grass median with a concrete median
  • A pedestrian crossing at the Cumberland Highway and Links Avenue intersection
  • Changes to the existing merge from south of the intersection with Cabramatta Road to south of the bridge over Cabramatta Creek.

Community engagement

We sought feedback from the community on the proposed improvements in January and February 2016. We received submissions from nine people during this consultation period.

In June and July we consulted the community about proposed design changes and our proposed night work construction schedule. We received five submissions during this consultation period.

We have prepared a Community Consultation Report which summarises the comments and responses from both feedback periods, as well as details of the decision.

What happens next?

We will continue to keep the community informed of the project as it progresses