Schofields Road is being upgraded to become a major east-west connection between Windsor Road and Richmond Road. Once this $340 million upgrade and extension is complete it will link the Rouse Hill and Marsden Park town centres and help to better meet the future transport needs of the North West Priority Land Release Area.

Schofield Road upgrade. © www.skyviewaerial.com.au

Updates and announcements

Night work on Tallawong and Hambledon Road, Schofields from Monday 9 January

Roads and Maritime Services is continuing to deliver this important project. As part of the work on Stage 2, we will be cleaning and connecting water main pipes from Tallawong Road to Hambledon Road on Schofields Road, Schofields.

To minimise traffic impacts, work will be carried out over four night shifts between Monday 9th January and Tuesday 31st January 2017, weather permitting. Our working hours will be from 6pm to 6am.

Day work will continue during standard construction hours between 7am and 6pm from Mondays to Fridays and between 8am and 1pm on Saturdays, excluding public holidays.

There will be some disruptions to the local water supply during this work. Sydney Water will notify affected residents directly before any disruptions occur.

View or download the December 2016 project notification (PDF, 191Kb).

Further updates are included in the October 2016 community update (PDF 3.68Mb).

Background

When the Schofields Road upgrade and extension to Richmond Road is complete it will form a tree lined transit boulevard linking the Rouse Hill and Marsden Park town centres and helping to meet the future transport needs of the North West Priority Land Release Area. Transit boulevards connect pedestrians, cyclists, public transport and vehicles with the surrounding urban land use and are tree lined to set them apart from other roads.

Schofields Road is currently a two-lane, rural road linking Windsor Road at Rouse Hill to Railway Terrace at Schofields. It forms a T-junction with Railway Terrace at its western end.

When the upgrade is completed, Schofields Road would cross the Blacktown-Richmond rail line via an underpass and continue via South Street to link up to Richmond Road at Marsden Park.

Schofields Road is part of an enormous program of NSW Government roadwork that is being planned and delivered in the North West Priority Land Release Area to support new residential and industrial centres in the area, which will see more than 70,000 new homes built in the next 20 years.

Schofields Road is being upgraded in three stages:

  • Stage 1 is between Windsor Road and Tallawong Road and was completed in June 2014
  • Stage 2 is between Tallawong Road and Veron Road and is being built
  • Stage 3 is between Veron Road and Richmond Road and is being built.

Benefits

The key benefits to the community include:

  • A direct local link between Windsor Road and Richmond Road
  • An east-west connection between the Rouse Hill Regional Centre, the proposed Sydney Metro Northwest (previously known as the North West Rail Link), the proposed new Schofields town centre, Schofields Railway Station and the proposed Marsden Park industrial, commercial and residential areas
  • An extra crossing of the Blacktown to Richmond railway line
  • Improved capacity along Schofields Road, catering for higher traffic volumes
  • 10 new intersections with traffic lights between Windsor Road and Richmond Road to improve accessibility for the North West Priority Land Release Area
  • Reduced travel times
  • Improved road safety
  • Improved access and safety for cyclists and pedestrians through off-road shared paths
  • Bus priority at key intersections
  • Improved landscaping
  • Improved flood immunity.

Photo gallery

What happens next?

  • Construction is expected to be completed by mid-2018, weather permitting