Intersection of Centennial Avenue and Epping Road, Lane Cove.

Centennial Avenue and Epping Road, Lane Cove intersection upgrade

The NSW Government is upgrading the intersection of Centennial Avenue and Epping Road. This will ease congestion and improve travel times.

Latest news

JAN 2019

JAN 2019Start of work

Roads and Maritime Services will widen Centennial Avenue by adding a left hand turn lane from Centennial Avenue onto Epping Road, helping to ease congestion, reduce travel times and make the intersection safer for northbound motorists.

Work starts on Monday 21 January 2019 and is planned to be completed by November 2019, weather permitting.

There will be up to five night shifts a week, for approximately 70 shifts, between late January and November.

Work hours are between 7am and 6pm Monday to Friday, 8am and 1pm on Saturday, and 6pm to 7am Sunday to Friday. No work will be done on public holidays.

This work schedule is designed to complete the intersection upgrade as quickly as possible, limiting the impact on the local community. Most work is being done at night to minimise traffic disruption and reduce health and safety risks to workers.

While there will be some noise associated with this upgrade – such as vehicle movements, concreting and moving equipment - every effort will be made to limit these disruptions. For example, nosier tasks will be completed by midnight and respite offered during prolonged night works.

Questions about any aspect of this project are welcome. Please contact Ward Civil at projects@wardcivil.com.au, 1300 919 508 or PO Box 1067 North Ryde BC 1670.

Updates on project progress will be available on this website and via letterbox drops in the local area.

Location of work at intersection of Centennial Avenue and Epping Road, Lane Cove.

Project information

The NSW Government is funding this intersection upgrade as part of its $300 million Urban Roads Pinch Point Program, which aims to reduce congestion and improve travel times on Sydney's busiest corridors.

Currently around 3800 vehicles an hour travel through the intersection of Centennial Avenue and Epping Road in the morning and afternoon peak periods. Northbound traffic on Centennial Avenue can experience significant delays and queues of more than 400 metres in the morning peak.

Roads and Maritime proposes to improve traffic flow through the intersection by widening Centennial Avenue and changing the lane configuration of Centennial Avenue and Epping Road.

Benefits of this intersection upgrade include:

  • Reduced queue lengths for motorists travelling northbound on Centennial Avenue at Epping Road
  • Improved travel times and left turn movement for northbound motorists turning from Centennial Avenue onto Epping Road.
  • Establishing a site compound in Turrumburra Park
  • Keeping the park’s pedestrian and bicycle access open and signposting essential detours
  • Diverting pedestrians using the footpaths along the park on Centennial Avenue and Epping Road
  • Widening the road to add a left turn lane on the southern approach to Centennial Avenue
  • Adjusting traffic lights
  • Modifying street lighting
  • Relocating utilities
  • Modifying the traffic island
  • Regrading and reinstatement of existing off-road cycle path
  • Improving stormwater drainage network.

There will be temporary traffic changes during work hours to ensure the work zone is safe. Please keep to speed limits and follow signs and traffic controller directions. For the latest traffic updates, call 132 701, visit livetraffic.com or download the Live Traffic NSW app.

Roads and Maritime would like to thank everyone who took the time to consider this proposal and provide feedback.

In response to requests from the community, the consultation period was extended to Wednesday 31 January 2018.

A report summarising feedback received and responses was published in April 2018.

We will continue to keep the community informed as the project progresses.

Project documents

Project notifications

Show filesHide files
File Title Size
January 2019 project notification

Work starts at Centennial Avenue and Epping Road, Lane Cove.

1.07Mb
October 2018 project notification

Centennial Avenue and Epping Road, Lane Cove Intersection upgrade – site compound establishment.

220Kb
February 2018 project notification

Investigation work – Proposed intersection improvements to Centennial Avenue and Epping Road, Lane Cove.

286Kb

Project updates

Show filesHide files
File Title Size
April 2018 project update

Proposed intersection improvements on Centennial Avenue and Epping Road, Lane Cove.

145Kb
December 2017 project update

Proposed improvements on Burns Bay Road, Centennial Avenue and Epping Road.

1.02Mb

Reports

Show filesHide files
File Title Size
April 2018 community consultation report

Centennial Avenue and Epping Road, Lane Cove intersection improvements.

1.23Mb

 

Contact us

For more information about this project please contact Ward Civil:

Phone: 1300 919 508

Email: projects@wardcivil.com.au

Post: PO Box 1067 North Ryde BC 1670.