Transport for NSW plans to upgrade the Parramatta Road, Wattle and Frederick Street intersection in Ashfield to improve traffic flow.
Construction commenced on 31 August 2020 and is expected to be completed by February 2021.
No work will happen on our site during the holidays from 5am Thursday 17 December 2020 to 8pm on Monday 4 January 2021.
Project information
The Parramatta Road, Wattle and Frederick Street intersection improvements commenced on 31 August 2020 and includes;
- minor changes to line markings to the intersection of Parramatta Road and Wattle Street
- modifying existing median strips on Parramatta Road to allow for simultaneous right turns from Wattle Street and Frederick Street
- upgrading storm water drainage, and
- relocating utilities.
The intersection upgrade work will improve traffic flow and allow for safer right turn movements from Wattle Street onto Parramatta Road.
We will commence the initial night work from Monday 31 August 2020 and the work is expected to be finished within 5 days, weather permitting.
The project is expected to be completed by February 2021.
Most of the work will be carried out during the night to reduce impacts to road users. Generally, our night work hours will be between:
- 8pm and 5am, Sunday to Thursdays
- no work on public holidays
Pedestrian access to the businesses and residential properties will be maintained.
Project documents
Project notifications
File | Title | Size |
---|---|---|
December 2020 project notification
Parramatta Road, Wattle and Frederick Street intersection upgrade. |
208Kb | |
November 2020 project notification
Footpath widening work - Campbell Road and Campbell Street community |
1.94Mb | |
August 2020 project notification
Start of work notification |
444Kb |
Contact us
For more information please contact the project team at Ventia Boral Amey Joint Venture:
Phone:1800 677 700
Email: nswenquiries@vbajv.com.au