Old Windsor Road, Bella Vista

The NSW Government has committed over $825 million to pinch point projects which ease congestion, reduce traffic delays and improve travel times on Sydney's major roads.

Widening Old Windsor Road between Norbik Drive and Seven Hills Road in Bella Vista (facing southwards)
Widening Old Windsor Road between Norbik Drive and Seven Hills Road in Bella Vista (facing southwards)

The NSW Government is funding this project as part of its $300 million Urban Roads Pinch Point Program, which aims to reduce congestion and improve travel time on Sydney’s busiest corridors.

Road users travelling between Sydney’s North West and Parramatta are experiencing congestion and long wait times on Old Windsor Road between Seven Hills Road and Norbrik Drive. To ease congestion, improve traffic flow and reduce travel times, we will:

  • Widen Old Windsor Road from two to three continuous lanes in each direction to ease congestion for motorists
  • Extend the right turn lanes from Old Windsor Road onto Seven Hills Road to improve southbound traffic flow.

Updates and announcements

Our upcoming work to widen Old Windsor Road, Bella Vista includes:

  • forming road pavement
  • installing new traffic signals and street lights
  • asphalting
  • line marking
  • removing temporary traffic barriers.

We will be working up to five days and five nights a week for 53 night shifts and 70 day shifts between Monday 1 July and Monday 30 September 2019, weather permitting.

Our day work hours will be between 7am and 6pm from Monday to Friday and between 8am to 1pm on Saturday. Our night work hours will be between 8pm and 5am from Sunday to Friday.

View the June 2019 project update (PDF, 375Kb) for more information.

Project background

The NSW Government is funding this project as part of its $300 million Urban Roads Pinch Point Program, which aims to reduce congestion and improve travel time on Sydney’s busiest corridors.

Road users are experiencing congestion and long wait times on Old Windsor Road between Seven Hills Road and Norbrik Drive. To ease congestion, improve traffic flow and reduce travel times, we are widening Old Windsor Road from two to three continuous lanes in each direction, extending the right turn lanes from Old Windsor Road onto Seven Hills Road and building a new northbound cyclist path connection from Old Windsor Road to the shared path on the Transitway.

Community benefits

The key benefits to the community include:

  • improving traffic flows on Old Windsor Road
  • improving safety for cyclists
  • easing congestion
  • reducing travel times.

We consulted on this project with the community in August and September 2017. View the results of the December 2017 consultation report.

What happens next

We will continue updating you on this project as work progresses, including informing you in advance about future work schedules and night work.