Old Windsor Road, Bella Vista

The NSW Government has committed over $825 million to pinch point projects which ease congestion, reduce traffic delays and improve travel times on Sydney's major roads.

Widening Old Windsor Road between Norbik Drive and Seven Hills Road in Bella Vista (facing southwards)
Widening Old Windsor Road between Norbik Drive and Seven Hills Road in Bella Vista (facing southwards)

The NSW Government is funding this project as part of its $300 million Urban Roads Pinch Point Program, which aims to reduce congestion and improve travel time on Sydney’s busiest corridors.

Road users traveling between Sydney’s North West and Parramatta are experiencing congestion and long wait times on Old Windsor Road between Seven Hills Road and Norbrik Drive. To ease congestion, improve traffic flow and reduce travel times, we will:

  • Widen Old Windsor Road from two to three continuous lanes in each direction to ease congestion for motorists
  • Extend the right turn lanes from Old Windsor Road onto Seven Hills Road to improve southbound traffic flow.

Updates and announcements

Start of construction was announced at Old Windsor Road in Bella Vista on 6 February 2019.

This stage of work includes:

  • continuing line marking and vegetation removal along this length of Old Windsor Road
  • removing asphalt and installing new temporary pavement for northbound lane and work zone access
  • earthmoving and constructing pavement
  • upgrading drainage.
  • installing permanent traffic signals and street lighting.

We will be updating you on this project as work progresses, including informing you in advance about future work schedules and night work.

Our work schedule

We will be on site for up to five days and five nights a week for 35 night shifts and 56 day shifts between Wednesday 10 April and Sunday 30 June 2019, weather permitting, excluding public holidays.

Our day work hours will be between 7am and 6pm from Monday to Friday and between 8am to 1pm on Saturday. Our night work hours will be between 8pm and 5am from Sunday to Friday. How will the work affect you?

Our work may be noisy at times. However we will do everything we can to minimise its impact, including completing noisier activities by midnight. Noise barriers along Old Windsor Road, will minimise the impact of noisy tasks. Traffic changes

There will be temporary traffic changes during our work hours to ensure the work zone is safe.

Lane closures will be in place and may affect travel times. Please keep to speed limits and follow signs and traffic controllers’ directions. For the latest traffic updates, you can call 132 701, visit livetraffic.com or download the Live Traffic NSW App.

Contact

If you have any questions, please contact the our delivery partner at toni.ford@georgiou.com.au or 0437 805 963.

For more information view or download the April 2019 project update (PDF, 421Kb).

What happens next

We will be updating you on this project as work progresses, including informing you in advance about future work schedules and night work.

The work will include:

  • widening Old Windsor Road to provide three lanes between Norbrik Drive and Seven Hills Road
  • extending the south-bound right turn bays on Old Windsor Road
  • building a new northbound cycleway connection from Old Windsor Road to a shared path on the T-Way
  • removing vegetation from the median.

Community benefits

The key benefits to the community include:

  • improving traffic flows and safety on Old Windsor Road, Bella Vista
  • improving safety for pedestrians and cyclists
  • reducing congestion and improved travel times.

Community consultation

We consulted on this project with the community in August and September 2017. To view the results of the report, view the December 2017 consultation report.

Project documents

 